<<<
Chronological Index
>>> <<<
Thread Index
>>>
Re: [gnso-wpm-dt] WPM Summary & Action Items-Step 6 (In Progress)
- To: Olga Cavalli <olgac@xxxxxxxxxxxxxxx>
- Subject: Re: [gnso-wpm-dt] WPM Summary & Action Items-Step 6 (In Progress)
- From: Stéphane Van Gelder <stephane.vangelder@xxxxxxxxx>
- Date: Mon, 15 Feb 2010 17:14:23 +0100
Thanks Olga.
Stéphane
Le 15 févr. 2010 à 17:04, Olga Cavalli a écrit :
> Stephane,
> I think that the group has gone through a process that has been long but
> constructive, if it was not made by the group the same questions and thougts
> would have been raised by the GNSO council as a whole when presenting a first
> approach.
> This is why I think it is constructive.
> I understand that it may sound frustrating from a private company
> perspective, but this is a group with multistakeholder views and processes
> are longer.
> As I said to Adrian, we are open to other suggestions and ideas. I know he
> will be the "read team" but in the mean time perhaps you or him can give us
> other ideas to move forward.
> As a group we should present our conclusions and outcomes in a face to face
> meeting in Nairobi.
> Others are also welcome to comment about Adrian an Stréphane´s concerns.
> Regards
> Olga
>
>
>
> 2010/2/15 Stéphane Van Gelder <stephane.vangelder@xxxxxxxxx>
> Olga,
>
> As group leader, what is your response to the issues raised by Adrian and
> myself?
>
> Do you feel the group should carry on along its present path?
>
> Stéphane
>
> Le 14 févr. 2010 à 22:59, Stéphane Van Gelder a écrit :
>
>> Adrian has joined us. He volunteered to red team the work.
>>
>> His latest comments make a lot of sense to me. The effort that's been put
>> into this work by this group has been immense. But it's not because someone
>> is working as hard as he can that he's working in the right direction.
>>
>> I've lately dropped back from the work being done on this group simply
>> because it has become, to me, unmanageable. The reason for that being the
>> extremely high level of complexity of some of the emails on this list and of
>> the proposed models. While we shouldn't shy away from complexity in our
>> search for the best solution, I think Adrian's point about how
>> prioritization works in an SME and about the length of time it is taking
>> this group to propose a method for prioritization should ring alarm bells
>> with us. When we started on this work in Seoul, did we really expect it
>> would take up to half a year to complete. I know I certainly didn't.
>>
>> We asked Adrian to red team. Part of doing that is putting his finger on the
>> things that we may not be seeing simply because we've got our noses pressed
>> against the problem all day while he is able to take a more distant look.
>>
>> I think we would do well to heed his alarm bells.
>>
>> Stéphane
>>
>> Le 14 févr. 2010 à 16:18, Olga Cavalli a écrit :
>>
>>> Thanks Adrian.
>>> We have been working as a group and trying to see all different points of
>>> views and ideas.
>>> You are welcome to join us an perhaps bring another perspective.
>>> Regards
>>> Olga
>>>
>>> 2010/2/14 Adrian Kinderis <adrian@xxxxxxxxxxxxxxxxxx>
>>> Team,
>>>
>>>
>>> Just watching from afar...
>>>
>>>
>>> I am very concerned that we are not making progress here. As a CEO of a
>>> medium size company we are prioritising work all the time. New tasks/
>>> projects come in all the time and changes are make dynamically. Nothing is
>>> set nor perfect. My Executive Management team provide input and the CEO
>>> makes the final decision. To me, that is why we have a GNSO Chair; to be
>>> the CEO.
>>>
>>>
>>> It has now been 4 months since Seoul and we have not seen any outward
>>> progress. I really think you have aimed for perfection and this has caused
>>> delay. Inexact prioritisation will not result in business lost, nor staff
>>> becoming unemployed. We may have small delays but the consequences are not
>>> critical.
>>>
>>>
>>> Let’s pick a process and roll forward, understanding and accepting its
>>> flaws.
>>>
>>>
>>> I know I haven’t been heavily involved and perhaps my comments aren’t
>>> helpful but I am seeing this process become more and more ICANN like...
>>> something I thought we were trying to avoid.
>>>
>>>
>>> Thanks.
>>>
>>>
>>> Adrian Kinderis
>>>
>>>
>>>
>>> From: owner-gnso-wpm-dt@xxxxxxxxx [mailto:owner-gnso-wpm-dt@xxxxxxxxx] On
>>> Behalf Of Ken Bour
>>> Sent: Saturday, 13 February 2010 9:54 AM
>>> To: gnso-wpm-dt@xxxxxxxxx
>>> Subject: [gnso-wpm-dt] WPM Summary & Action Items-Step 6 (In Progress)
>>>
>>>
>>> WPM Team Members:
>>>
>>>
>>> Following is a summary of the WPM teleconference held on 9 February 2010
>>> (1700 UTC):
>>>
>>>
>>> Team Decisions:
>>>
>>>
>>> 1) Urgency: Jamie and Ken reported on their email exchanges between
>>> sessions and, after additional consideration during this teleconference,
>>> the team agreed that, although “urgency” represented an intriguing
>>> potential modeling concept, to make use of it properly would require an
>>> objective measurement which does not appear feasible. The team agreed that
>>> urgency/criticality should become a natural part of the Value/Benefit
>>> assessment and the definition will be enhanced to include that concept (see
>>> Action Items below).
>>>
>>>
>>> 2) Resources Needed: Ken recommended dropping this dimension as well
>>> as the 4-quadrant model for reasons provided in his earlier email (8 Feb
>>> 2010). After discussing the pros/cons, the team agreed to simplify its
>>> model to a one-dimensional rating of Value/Benefit. There was also
>>> consensus that, rather than discard Resources Needed entirely, it could
>>> serve as a potential tie-breaker if a decision had to be made between two
>>> projects that were otherwise tied on Value/Benefit. The process would be
>>> as follows:
>>>
>>> Step 1: Rate all projects using the 1-7 scale on Value/Benefit
>>> Step 2: If needed as a tie breaker, rank any tied projects using Resources
>>> Needed
>>>
>>>
>>> [Note: Jamie suggested that the team reconsider the terminology/title of
>>> “Resources Needed” preferring a return to the original concept of perceived
>>> “Difficulty.” Ken will include this question in a separate email
>>> transmitting revised definitions for team review.]
>>>
>>>
>>> Once these decisions were concluded, the team took up another important
>>> Step 6 question, “How will the Council actually utilize a prioritization?
>>>
>>>
>>> As framework for this discussion, Ken posited that a work prioritization
>>> exercise presupposes that there is some limitation of a scarce commodity
>>> (e.g. resource capacity). If there is an abundance of time and resources
>>> and no real constraints, there would be no obvious need for a project
>>> ranking. The underlying assumption is that, due to immovable constraints
>>> (in the short run), all project work cannot be undertaken simultaneously.
>>> A prioritization, then, presumes that hard decisions are expected based on
>>> competing interests for scarce resources, e.g. perform A instead of B or
>>> move staffing from one project to another. If it turned out that, after
>>> developing a prioritization, no project ever slowed down, stopped, or had
>>> its resources altered, a reasonable question might be: what was the
>>> purpose or value in generating the prioritization?
>>>
>>>
>>> Chuck acknowledged that we cannot assume that projects can be eliminated or
>>> postponed simply because they have a low position on relative priority.
>>> Looking at the bottom projects test-ranked by the WPM team (e.g. GEO,
>>> TRAV), he was able to articulate convincing reasons why they probably can
>>> and should be continued even though they occupy the lowest positions on the
>>> ranking list.
>>>
>>>
>>> This discussion led to a hypothesis that, perhaps, the model may not be as
>>> useful in making stop/pause decisions about existing work, but may be more
>>> useful in deciding what to do with new projects that are introduced after
>>> the initial prioritization is performed (e.g. Vertical Integration).
>>>
>>>
>>> The first question considered was: how should a new project be
>>> rated/evaluated and placed into the prioritization mix? The team reached
>>> agreement on an approach to placing a new project into the ranking.
>>> Assuming that the Council will complete a full prioritization at least
>>> quarterly (TBD), it would never be more than 3 months between rating
>>> sessions. Presuming that Councilors could readily recall what they did the
>>> last time, if a new project surfaces in the interim and cannot wait until a
>>> new quarterly reprioritization, the Council would employ the same technique
>>> that generated the most recent list. For example, 4-5 small groups of
>>> Councilors would meet and collectively vote/decide on a rating from 1-7
>>> considering the same “average project” that was used at the last rating
>>> session. Once a median rating is computed from the group consensus scores,
>>> the new project would take its appropriate slot in the ranking. [Note:
>>> Ken will flesh out this procedure when we get to the point of preparing
>>> Council instructions.]
>>>
>>>
>>> Once a new project is placed into the prioritized list, Chuck suggested
>>> that there might be a sequence of questions that should be asked/answered
>>> by the Council in deciding what to do with it. Perhaps the team could
>>> create a map or process that the Council would use in evaluating a new
>>> project vis a vis the existing workload.
>>>
>>>
>>> In addition to assessing a new project, Jamie ventured that there might be
>>> a political value in performing the prioritization even if there is not a
>>> clear decision-making role related to stopping or postponing existing work.
>>> He commented that a project prioritization can establish for the entire
>>> organization (top to bottom) an understanding as to how all work relates to
>>> the GNSO’s primary mission and goals.
>>>
>>>
>>> In thinking about this political implication, Ken wondered if there might
>>> be a potential drawback to publishing a project ranking. Taking the worst
>>> possible scenario, hypothetically, might certain teams working on the
>>> lowest ranked projects perceive that their time/effort is not worth
>>> continuing? The WPM team should think carefully through possible morale
>>> implications to be certain that a new problem isn’t created,
>>> unintentionally, that wasn’t there before this exercise began. In response
>>> to this question, Olga thought that it would be possible to underscore that
>>> projects ranked at the bottom do not necessarily imply a fundamental lack
>>> of worth. On the other hand, following Jaime’s concept of political
>>> prioritization, a project ranking does communicate overall importance. The
>>> Council may not want to suggest, subtly or overtly, that volunteers should
>>> know or even think about any project’s relative value in deciding which
>>> team(s) to join – only their interest and expertise concerning the work
>>> itself.
>>>
>>>
>>> Action Items:
>>>
>>>
>>> In addition to the above summary, Ken agreed to complete the following
>>> tasks between now and the next meeting (16 February, 1700 UTC).
>>>
>>>
>>> 1) Suggest draft changes to both Y and X definitions for team
>>> discussion and approval at the next WPM meeting.
>>>
>>>
>>> 2) Identify additional Step 6 questions (e.g. group/individual
>>> methodology) that the team needs to consider.
>>>
>>>
>>> 3) Continue discussion, as challenged by Jaime: What is/are the real
>>> outcome(s) of the prioritization? Can the team provide concrete and
>>> persuasive answers to this question that would satisfy others who have not
>>> been deeply involved with the process (e.g. “Red Team”)?
>>>
>>>
>>> 4) Ken proposed that the team also consider making a recommendation
>>> related to the implementation of desperately needed project management
>>> tools for both Staff & Community to assist with the Council’s new
>>> “managerial” role in the policy development process.
>>>
>>>
>>> Since this summary is already long, the above topics will be included in
>>> one or more separate emails so that the team can focus on the topics more
>>> efficiently and effectively.
>>>
>>>
>>> Prepared by:
>>>
>>>
>>> Ken Bour
>>>
>>>
>>>
>>
>
>
<<<
Chronological Index
>>> <<<
Thread Index
>>>
|