WG formed, chair & Council liaison & staff coordinator identified,
Sydney Workshop Complete = T
Initial public comment completed: T + 21
Template for constituency comments completed: T + 21 days 
Constituency comments due: T + 70 days 
Initial Report: T + 110 days 
First comment period ends: T + 131 days 
Preliminary Final Report: T + 161 days
Tim
 
 
 
<<<