 Re: [gnso-ppsc-wg] Your feedback requested - Section 6.2.2.3 Deliverables and Timeframes
To: Marika Konings <marika.konings@xxxxxxxxx>Subject: Re: [gnso-ppsc-wg] Your feedback requested - Section 6.2.2.3 Deliverables and TimeframesFrom: "S. Subbiah" <subbiah@xxxxxxxxx>Date: Wed, 19 May 2010 10:52:13 -0700 
 
Clearly in prcatice the comment is right - even our WG has taken way 
longer. 
I suggest modifing  current
A Charter is expected to include some, if not all, of the following 
elements: potential outcomes and/or expected deliverables, key 
milestones, and a target timeline. 
to
A Charter is expected to include some, if not all, of the following 
elements: potential outcomes and/or expected deliverables, key 
milestones, and a target timeline - all of which can, if necessary, be 
further refined by the WG at its onset in conjunction with the CO. 
Subbiah
Marika Konings wrote:
 
*6.2.2.3 Deliverables and Timeframes
*
A Charter is expected to include some, if not all, of the following 
elements: potential outcomes and/or expected deliverables, key 
milestones, and a target timeline. Although the identification of 
specific work tasks, outcomes, and deadlines might be perceived as 
constraining the WG in its activities, it is also intended to provide 
guidance to the WG and prevent unintentional scope creep. It should be 
emphasized that the WG can always ask the CO to reconsider any of the 
deliverables or renegotiate deadlines identified by providing its 
rationale. 
In certain WGs, such as a Policy Development Process, the milestones 
and timeline might be prescribed by the ICANN Bylaws. In other 
situations, sufficient thought should be given to key milestones, 
realistic timelines, and ways to inform and consult the ICANN 
Community (such as public comment periods). It should be noted that 
any changes to milestone dates incorporated in the charter will need 
to be cleared wit the CO. 
------------------------------------------------------------------------
*Comments:
*
CG: It may not always be possible to set timeframes in the charter. 
There likely will be situations when the WG itself will need to be 
tasked with producing a list of deliverables and an estimated 
timeframe. It is suggested that the wording of this paragraph be 
adjusted to accommodate that.
 
 
 <<<