Hi,
I would just like to point out that it may require more then meeting
per week to get finished. We can use part of the Thursday meeting
to figure out exactly what needs to be completed in order to meet
these dates.
thanks
a.
On 26 jun 2007, at 13.05, Liz Williams wrote:
Colleagues
I have put together some dates which may be helpful to the group in
preparing the next stage of the work plan. You will see that we
have a lot to cover in a very short time frame if we are to have
ready a Board Report for consideration around the LA meeting in
late October.
If we are to have a Board Report ready for consideration at the LA
meeting then we, working backwards, need to:
1. Have the Board Report ready and in the General Counsel's hands
11 days prior to the 2 Nov Board meeting -- 22 October
2. Internal sign off and final check 14 days prior to preparation
of Board Report -- 8 October
3. 20 day public comment period on GNSO Council Final Report --
allowing time for inclusion of results in the Final Report say 30
days -- 8 September public comment period needs to start. Public
comments will be included in the Board Report.
4. Final Report will need to be with Council 7 days prior to the
meeting to vote on it -- release 1 September (Part A, Part B, draft
RFP, draft base contract and draft implementation plan) and meeting
7 September
5. That means we need to complete the final negotiations of the
Committee by, at the latest, 10 August.
The first 4 dates are fixed in either the bylaws or the board
reporting guidelines.
I suggest that we schedule, after Thursday this week, 2 more
Committee conference calls to wrap up last details. I suggest
Thursday 5 and 12 July at 2pm Brussels time. I will also hold
other dates -- 19 July and 27 July. I will need a period of time
to complete the writing and release the Council Report without
ongoing negotiation.
Kind regards.
Liz
.....................................................