RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed schedule for remaining work
- To: "Marilyn Cade" <marilynscade@xxxxxxxxxxx>, "'Cubberley, Maureen \(CHT\)'" <MCubberley@xxxxxxxxx>, "'GNSO.SECRETARIAT@xxxxxxxxxxxxxx'" <gnso.secretariat@xxxxxxxxxxxxxx>, <pdp-pcceg-feb06@xxxxxxxxxxxxxx>
- Subject: RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed schedule for remaining work
- From: "David W. Maher" <dmaher@xxxxxxx>
- Date: Mon, 26 Jun 2006 20:07:43 -0500
Thank you, Marilyn.
David
At 03:50 PM 6/26/2006, Marilyn Cade wrote:
I can do any dates that week. I am in Missouri
the end of the previous week at a memorial
service for my father, setting his stone and
planning trees in his memory, so all will
understand that isn?t really feasible, but I can
possibly travel on Monday and start the week
earlier? if that helps David?s conflicts. Marilyn Cade
----------
From: owner-pdp-pcceg-feb06@xxxxxxxxx
[mailto:owner-pdp-pcceg-feb06@xxxxxxxxx] On Behalf Of David W. Maher
Sent: Monday, June 26, 2006 11:31 AM
To: Cubberley, Maureen (CHT);
GNSO.SECRETARIAT@xxxxxxxxxxxxxx; pdp-pcceg-feb06@xxxxxxxxxxxxxx
Cc: Maureen Cubberley
Subject: Re: [pdp-pcceg-feb06] PDP Feb 06 Task
Force - proposed schedule for remaining work
I have conflicting commitments for Sept 20 ,21 and 22.
David Maher
At 05:58 AM 6/26/2006, Cubberley, Maureen \(CHT\) wrote:
Good morning All,
Further to our meeting yesterday, I wish to
propose a timeline that takes us from here to
the December meeting in São Paulo.
This e-mail incorporates many of the points in
the earlier e-mail that circulated yesterday
morning, under the subject, ?Marrakech Update?
and also incorporates the dates that were
included in Bruce?s PowerPoint presentation at
the GAC meeting yesterday afternoon.
There are two areas where responses to this e-mail are requested.
Question Number 1.
September 20, 21 and 22 have been proposed as
the dates for a face-to-face meeting. The
location has not yet been determined, however,
Los Angeles has been discussed as a likely
location. Please indicate your availability for these dates.
Question Number 2.
Liz Williams has proposed developing a program
and schedule to identify and deliver expert
materials and expert advice to the task force.
Please provide your recommendations for either
materials or experts, as discussed yesterday.
Kindly reply to the entire Task Force list.
Proposed Schedule for Remaining Work.
1. July 15
Confirmation of schedule for remaining work.
(This proposal or some amended version thereof.)
2. Throughout Month of August
Seek expert advice. (including literature
search and webinar involving expert individuals)
3. September 13th
Complete drafting of Preliminary
Report, and circulate to Task Force members.
4. September 20, 21, and 22
Face-To-Face Meeting of Task Force members.
Among the agenda items:
- Discussion of impact of expert
advice on terms of reference and on drafting of Final Report.
- Discussion of public comment on
terms of reference and on drafting of Final Report
5. October
Finalization of Preliminary Report
Posting for Public Comment
6. November
Draft Final Report circulated to Task Force members
7. December
Meeting in São Paulo
- Finalize decisions on content for final report
Looking forward to your response and input to this draft schedule.
With thanks,
Maureen
Maureen Cubberley, Chair PDP Feb 06 TF
<<<