 Re: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  schedule for remaining work
To: "Cubberley, Maureen ((CHT))" <MCubberley@xxxxxxxxx>Subject: Re: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  schedule for remaining workFrom: Liz Williams <liz.williams@xxxxxxxxx>Date: Mon, 31 Jul 2006 08:32:18 +0200 
 Colleagues 
 Thanks for your thoughts on an updated schedule. 
 I expect the report will be released sometime this week. Could I please urge you all to send to me any further suggestions for  
expert materials as they relate to the terms of reference.  I have,  
so far, had only one response.
 
 I would suggest that it is premature to consider the necessity of a  
face to face meeting outside a regular ICANN meeting until the TF has  
considered the expert materials and then considered the report as it  
stands in light of those materials.
 
 
 Liz
..................................................... 
 Liz Williams
Senior Policy Counselor
ICANN - Brussels
+32 2 234 7874 tel
+32 2 234 7848 fax
+32 497 07 4243 mob 
 
 
 On 28 Jul 2006, at 21:27, Cubberley, Maureen ((CHT)) wrote:
 
 Hi Jon, 
 
 The location hasn't been determined yet, but Washington, DC and Los  
Angeles are the two venues that have been discussed.
 
 
 
 Good point about participation in the Council calls. Thanks. It is  
probably still useful to discuss it during the Council  
teleconference, and then get input from the rest of the Task Force  
either by e-mail or a very short teleconference.  If we go the  
teleconference route I would suggest that we schedule it as soon as  
possible. Perhaps immediately after Thursday's council call?
 
 
 
 
 Maureen 
 
 
 
 From: owner-pdp-pcceg-feb06@xxxxxxxxx [mailto:owner-pdp-pcceg- 
feb06@xxxxxxxxx] On Behalf Of Nevett, Jonathon
 Sent: Friday, July 28, 2006 1:21 PM
 To: Liz Williams; pdp-pcceg-feb06@xxxxxxxxxxxxxx; Glen de Saint Gery
 Subject: RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 Maureen: 
 
 Either set of meeting dates are ok with me.  What location do you  
have in mind?  Please keep in mind that not all of the Task Force  
Members participate in Council calls.
 
 
 
 
 Thanks. 
 
 
 Jon 
 
 From: owner-pdp-pcceg-feb06@xxxxxxxxx [mailto:owner-pdp-pcceg- 
feb06@xxxxxxxxx] On Behalf Of Cubberley, Maureen (CHT)
 Sent: Friday, July 28, 2006 2:07 PM
 To: Liz Williams; Marilyn Cade; pdp-pcceg-feb06@xxxxxxxxxxxxxx;  
Glen de Saint Gery; David W. Maher
 Subject: RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 Good morning All, I have been in e-mail correspondence with Liz Williams regarding an  
updated schedule all the work for the PDP Feb 06 Task Force.
 
 The schedule that follows is based on Liz's draft schedule and  
contains my proposed revisions, particularly with regard to meeting  
dates, and some sequencing of items.
 
 Regrettably, I was unable to participate in the last Council  
teleconference, and according to the minutes in the MP3 there was  
some discussion about the timing of soliciting advice and dialogue  
with anti-trust and competition experts, and on the date of the  
next Task Force meeting.
 
 I have proposed dates for both of these items in this revised  
schedule.
 
 Two sets of dates for the next meeting of the task force are  
included here - two days in September or two days in October.   
These dates are based on indications of availability by individual  
Task Force members at the Marrakesh meeting, and also on the recent  
request to come up with more than one option for dates.  Please  
note, I have not yet been able to run these dates by ICANN Staff.
 
 I also ask that we add discussion of this schedule to our agenda  
for the Council teleconference, which will be held next Thursday,  
August 3. I realize that this addition is one day late for the one- 
week notice of agenda items.  However, there is no documentation to  
be read and considered other than this e-mail, so I would ask the  
Council's and Chair’s indulgence in adding this item to next week's  
agenda.
 
 
 
 
 Proposed Work Schedule for PDP Feb-06 Task Force 
 
 
 WEDNESDAY, AUGUST 2 
 
 1. Distribution of an updated version of the Preliminary Report on  
PDP-Feb06 - Contractual conditions for existing gTLDs, which will  
include the input from the Marrakech meeting.
 
 2. Cut off date for recommendations for expert materials and expert  
advisors.
 
 
 
 
 THURSDAY, AUGUST 3 
 
 3. Confirmation of this or an agreed-upon revised schedule during  
the Council teleconference.
 
 
 
 
 FRIDAY AUGUST 11 4. Distribution of the PDP Feb 06 Expert Materials Collection for  
the use of the Task Force Members throughout August and the first  
part of September (Discussion Item:  making these materials  
available on the GNSO website.)
 
 
 
 
 SEPTEMBER 19 AND 20TH, or OCTOBER 12 AND 13 
 5. Task Force Meeting - consider expert materials and decide whether further advice from  
in person experts is needed.
 
 -discuss drafting of Final Report; identify specific changes and  
additions to move report from preliminary status to Final Report.
 
 
 
 FRIDAY OCTOBER 20TH (if Task Force meeting is in September) or  
FRIDAY, NOVEMBER 10 (if Task Force meeting is in October)
 
 6. Final Report released to the GNSO Council for discussion (and  
subsequent forwarding to the ICANN Board at the São Paulo meeting).
 
 
 
 That’s it so far. Kindly respond to the proposed dates for the Task  
Force meeting prior to the Council teleconference next Thursday.   
It will save us some time if we have an indication of everyone’s  
availability. Thank you.
 
 
 
 
 Best regards, 
 Maureen. 
 
 
 
 
 
 
 
 From: owner-pdp-pcceg-feb06@xxxxxxxxx [mailto:owner-pdp-pcceg- 
feb06@xxxxxxxxx] On Behalf Of Liz Williams
 Sent: Friday, July 28, 2006 2:00 AM
 To: Marilyn Cade
 Cc: pdp-pcceg-feb06@xxxxxxxxxxxxxx
 Subject: Re: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 Dear Colleagues 
 
 I have prepared a draft work schedule which is just going through  
the mill now -- my apologies for the delay.  We have a very heavy  
workload between now and Sao Paolo (nothing new there) but we do  
want to be sure that we have as few deadline clashes as possible.
 
 
 
 I have been concentrating heavily on the new TLDs PDP and other  
projects and this has slipped through my little net.
 
 
 
 
 My apologies -- should be done ASAP. 
 
 
 Liz 
 ..................................................... 
 
 
 Liz Williams 
 Senior Policy Counselor 
 ICANN - Brussels 
 +32 2 234 7874 tel 
 +32 2 234 7848 fax 
 +32 497 07 4243 mob 
 
 
 
 
 
 
 
 
 On 28 Jul 2006, at 00:56, Marilyn Cade wrote: 
 
 We have lost a lot of time and some flexibility due to the gap of  
time. It is critical to have more than one option for dates.
 
 
 Regards, 
 Marilyn Cade 
 
 
 
 
 -----Original Message----- 
 From: "Cubberley, Maureen \(CHT\)" <MCubberley@xxxxxxxxx> 
 Date: Thu, 27 Jul 2006 15:09:31 To:"David W. Maher" <dmaher@xxxxxxx>, "Liz Williams"  
<liz.williams@xxxxxxxxx>,       "Marilyn Cade"  
<marilynscade@xxxxxxxxxxx>
 
 Cc:<jnevett@xxxxxxxxxxxxxxxxxxxx>,  
<gnso.secretariat@xxxxxxxxxxxxxx>,       <pdp-pcceg- 
feb06@xxxxxxxxxxxxxx>, <m.cubberley@xxxxxxxxxxxx>
 
 Subject: RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed   
schedule for remaining work
 
 
 
 
 Hi David, 
 
 
 
 
 ………. am working on it as we speak, and I will get back to you by  
mid-day tomorrow latest. Sorry for the delay.
 
 
 
 
 
 
 Best regards,
 
 
 
 
 
 Maureen
 
 
 
 
 
 
 
 
 
 ----------------
 
 
 
 From: David W. Maher [mailto:dmaher@xxxxxxx] 
  Sent: Thursday, July 27, 2006 3:02 PM 
  To: Liz Williams; Marilyn Cade Cc: jnevett@xxxxxxxxxxxxxxxxxxxx; Cubberley, Maureen (CHT);  
gnso.secretariat@xxxxxxxxxxxxxx; pdp-pcceg-feb06@xxxxxxxxxxxxxx;  
m.cubberley@xxxxxxxxxxxx
 
 Subject: Re: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 
 
 Do we have a scheduled date yet?
 
  thanx 
  David 
 
 
  At 12:16 AM 7/11/2006, Liz Williams wrote: 
 
 
 
 
 
 
 Dear All 
 
 
  Apologies for silence from my end -- I am now back on deck. 
 
 I will speak to Maureen later my today and come up with some  
solutions.  I realise everyone is anxious to get the dates sorted  
quickly and I'll do my best to ensure that happens by end of the  
week this week.
 
 
 
 
  Kind regards. 
 
 
  Liz 
  ..................................................... 
 
 
  Liz Williams 
  Senior Policy Counselor 
  ICANN - Brussels 
  +32 2 234 7874 tel 
  +32 2 234 7848 fax 
  +32 497 07 4243 mob 
 
 
 
 
 
 
 
 
  On 11 Jul 2006, at 02:29, Marilyn Cade wrote: 
 
 
 
 
 
 
 
 recall that some had problems with the last part of the week and  
were asking for earlier in week, due to religious holidays. I think  
we had seen support for that... can we get a new proposal from  
staff on which dates? and are we set on L.A.?
 
 
 
 Is so, fine by me. as long as we get dates confirmed so we can all  
buy cheap fares. :-)
 
 
 
 I am awre that it is expensive to rent a hotel meeting room/do  
the logistical set up. IF you decide you want to borrow the AT&T  
facility again, in DC please let me know. there is still some cost  
for physical set up, but the staff tehre have reinstalled an audio  
card in the overhead bridge. and have hand microphones/stands that  
can be used. the system was not operational for our last meeting  
due to an audio card outage taht occurred with no backup. They have  
solved taht problem, they tell me. . The staff did install a  
wireless network specifically for our use and will reactivate that.
 
 
 
 On the other hand, if the meeting is in la. I would assume that  
the ICANN technial team will handle the set up/technical support  
for the meeting, so that is a benefit to meeting in LA.
 
 
 
 
 However, you need to let me know asap if you want to see if the  
room is avialable. I looked into the cost of airfare and it is  
pretty much the same betwen DC and LA for most attendees. The  
difference imight be the extratime/flight for Bruce to come to DC,  
and for Alistair, who would also be coming from points Asia.
 
 
 
 
 In any case, can we see optional dates from staff taking into  
account the feedback on the religious holiday, and a final decision  
on site?
 
 
 
 
 Mairyn
 
 
 
 
 
 
 
 
 
 
 
 From: "Nevett, Jonathon" < jnevett@xxxxxxxxxxxxxxxxxxxx> 
 
 To: "Cubberley, Maureen (CHT)" <MCubberley@xxxxxxxxx>, "  
GNSO.SECRETARIAT@xxxxxxxxxxxxxx" <
 
 gnso.secretariat@xxxxxxxxxxxxxx:  
<mailto:gnso.secretariat@xxxxxxxxxxxxxx> >, < pdp-pcceg- 
feb06@xxxxxxxxxxxxxx>
 
 
 
 
 CC: "Maureen Cubberley" <m.cubberley@xxxxxxxxxxxx > 
 
 Subject: RE: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 Date: Mon, 10 Jul 2006 17:06:34 -0400 
 
 Are we set with a September meeting in LA?  Let’s lock in the  
dates.  As Marilyn stated, the longer we wait the more expensive it  
will get.  Thanks.  Jon
 
 
 
 
 
 
 
 
 ----------------
 
 
 From: owner-pdp-pcceg-feb06@xxxxxxxxx [ mailto:owner-pdp-pcceg- 
feb06@xxxxxxxxx] On Behalf Of Cubberley, Maureen (CHT)
 
 
 
 
 Sent: Monday, June 26, 2006 6:59 AM 
 
 To: GNSO.SECRETARIAT@xxxxxxxxxxxxxx; pdp-pcceg- 
feb06@xxxxxxxxxxxxxx: <mailto:pdp-pcceg-feb06@xxxxxxxxxxxxxx>
 
 
 
 
 Cc: Maureen Cubberley 
 
 Subject: [pdp-pcceg-feb06] PDP Feb 06 Task Force - proposed  
schedule for remaining work
 
 
 
 
 
 
 
 
 
 
 Good morning All, 
 
 
 
 
 Further to our meeting yesterday, I wish to propose a timeline that  
takes us from here to the December meeting in São Paulo.
 
 
 
 
 
 
 This e-mail incorporates many of the points in the earlier e-mail  
that circulated yesterday morning, under the subject, “Marrakech  
Update” and also incorporates the dates that were included in  
Bruce’s PowerPoint presentation at the GAC meeting yesterday  
afternoon.
 
 
 
 
 
 
 There are two areas where responses to this e-mail are requested.
 
 
 
 
 
 Question Number 1.
 
 
 September 20, 21 and 22 have been proposed as the dates for a face- 
to-face meeting.  The location has not yet been determined,  
however, Los Angeles has been discussed as a likely location.   
Please indicate your availability for these dates.
 
 
 
 
 
 
 
 
 
 
 Question Number 2. 
 
 Liz Williams has proposed developing a program and schedule to  
identify and deliver expert materials and expert advice to the task  
force.
 
 
 
 Please provide your recommendations for either materials or  
experts, as discussed yesterday.
 
 
 
 
 Kindly reply to the entire Task Force list. 
 
 
 
 
 
 
 
 
 Proposed Schedule for Remaining Work. 
 
 
 
 
 
 
 
 
 1. July 15 
 
 Confirmation of schedule for remaining work. (This proposal or some  
amended version thereof.)
 
 
 
 
 
 
 2. Throughout Month of August
 
 
 Seek expert advice.  (including literature search and webinar  
involving expert individuals)
 
 
 
 
 
 
 
 
 
 
 3. September 13th 
 
 Complete drafting of Preliminary Report, and circulate  
to Task Force members.
 
 
 
 
 
 
 
 
 
 
 4. September 20, 21, and 22 
 
 
             Face-To-Face Meeting of Task Force members. 
 
 
 Among the agenda items: 
 
 -           Discussion of impact of expert advice on terms of  
reference and on drafting of Final Report.
 
 
 
 -           Discussion of public comment on terms of reference and  
on drafting of Final Report
 
 
 
 
 
 
 
 
 
 
 5. October 
 
 
             Finalization of Preliminary Report 
 
 
             Posting for Public Comment 
 
 
 
 
 6. November
 
 
 
             Draft Final Report circulated to Task Force members 
 
 
 
 
 7. December
 
 
 
             Meeting in São Paulo 
 
 
 -           Finalize decisions on content for final report 
 
 
 
 
 
 
 
 
 
 
 Looking forward to your response and input to this draft schedule.
 
 
 
 
 
 With thanks,
 
 
 
 Maureen 
 
 
 
 
 Maureen Cubberley, Chair PDP Feb 06 TF
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 <<<