<<<
Chronological Index
>>> <<<
Thread Index
>>>
Re: [gnso-ppsc-pdp] Your input requested - recommendation 14 - Efficiency and flexibility during the planning / request for an Issues Report phase
- To: "Gnso-ppsc-pdp@xxxxxxxxx" <gnso-ppsc-pdp@xxxxxxxxx>
- Subject: Re: [gnso-ppsc-pdp] Your input requested - recommendation 14 - Efficiency and flexibility during the planning / request for an Issues Report phase
- From: Alan Greenberg <alan.greenberg@xxxxxxxxx>
- Date: Thu, 20 May 2010 09:30:12 -0400
It is fine for Council to "negotiate" with regard
to Issue Reports the *IT* requests. I am totally
against the GNSO Council having the right to
negotiate on behalf of Issue Reports that it did
not initiate. This give Council the ability to
effectively defer on an issue that it has no
interest in without even having the issues
presented to it. This takes a lot of power out of
having alternative methods of initiating the PDP
process. And at best adds months to the process.
Alan
At 20/05/2010 08:56 AM, Avri Doria wrote:
Hi,
I stil think that the Staff should be given a
week to asses the work requirements versus
existing load and should give an estimate that
the council can then negotiate with them.
I do not see much value in the ranges or tops
ends - every schedule tends toward the outside
edge of a range since that is the most
comfortable for those who have to schedule the
work. I think if should rest on a realistic
case analysis. We can be sure that if the Staff
were to come back with a ridiculous estimate
thee would be someone in the council to question
it. not that I would expect this to happen - as
a professional staff, I believe the Policy Staff
takes pride in its ability to get the work done
in a timely manner and to give accurate measurements.
a.
On 11 May 2010, at 05:47, Marika Konings wrote:
> For discussion / consideration:
>
> ? The recommendation for item 7 -
Community input / How to incorporate public
comments would also apply here: A decision is
needed on the timeframe for the delivery of an
issues report. The WT could consider putting
forward a number of different ranges for
community consideration e.g. within thirty (30)
calendar days / forty-five (45) calendar days /
a period determined by the GNSO Council. The WT
might also want to consider allowing the
Council to modify this timeframe if it is
deemed that additional research / discussion is
required to develop an informed and balanced Issues Report.
>
> From PDP-WT Draft Conclusions and Recommendations Updated 11 May
>
> 9. Efficiency and flexibility during planning
/ request for an issues report phase
>
> Recommendation 14.
>
> § To be decided [Recommendations suggested
for issue 7 could also apply here]
>
> Efficiency and flexibility during planning /
request for an issues report phase
>
> Current rules and practice
>
> From ICANN by-laws:
> Within fifteen (15) calendar days after
receiving either (i) an instruction from the
Board; (ii) a properly supported motion from a
Council member; or (iii) a properly supported
motion from an Advisory Committee, the Staff
Manager will create a report (an "Issue Report")
>
> Concerns / Questions
>
> 9.a Current deadline of 15 days
after receipt of a request is unworkable. How
to build in sufficient flexibility to allow for
additional research and consultation when
needed, while being able to move forward
quickly in those cases where additional work is
not deemed necessary? Would a flexible
timetable be an option i.e. in the request the
submitting party with staff support develops a
draft timeline which can consist of a number of
phases that are pre-determined with a set timeframe?
> 9.b What flexibility should be
foreseen for additional research or study at the initiation phase?
>
>
> PDP WT Response
>
> 9.a It was suggested that a drafting
team that is tasked with developing a charter
for a WG should also be in a good position to
develop a realistic timeline for delivery of
the milestones. Some suggested a maximum
deadline of 30 days or 45 days that could be
extended but only with the agreement of the
requester. Others suggested to include target
dates in the by-laws based on the current
experience with PDP timelines, but with the
flexibility for modification by the GNSO
Council if it is deemed necessary to allow for
extra time for research or consultation. It as
also suggested that guidance could be provided
on how much additional time should be needed
for certain additional elements such as a
workshop or public comment period during the
planning and initiation phase. Some noted that
this should be left to the Council to decide on
a case-by-case basis, with input from Staff as
to their current workload and estimate of time
to complete each project. Others noted !
that the timeline should be driven by the
complexity of the issue but within a certain
date boundary set out. Some suggested that
there should be two types of requests, one
standard request, which would be queued behind
exiting requests / reports, and a second
expedited / urgent request which would move up
to the queue if it has broad support of
multiple SO/ACs and/or the Board or GNSO Council.
> 9.b Some suggested that flexibility
should be retained, but that research or study
can occur after the initiation phase. Some
indicated that research / study at this stage
should be minimized. Others suggested that
there should be flexibility at all stages.
<<<
Chronological Index
>>> <<<
Thread Index
>>>
|